Construction Schedule – Route 44 Safety Improvement Project

Good Afternoon,

The Route 44 (Albany Avenue) Safety Improvements Project website has been updated with the following new schedule content: 

Schedule: Week of May 4, 2020*

Normal Work Hours: 7:00am – 5:00pm, Monday-Friday

  • Flower, ornamental grass, and shrub planting begin this week on Albany Avenue. Tree planting continues.
  • Sidewalk demolition will occur on the north side of Albany Avenue between Irving and Magnolia Streets.
  • Sidewalk and driveway apron installation is scheduled for the north side of Albany Avenue between Irving and Garden Streets.
  • Traffic signal installation continues all week at the intersection of Garden Street and Albany Avenue.  The installation of traffic signals will begin at the Vine Street intersection.
  • Installation of electrical conduit and decorative lighting continues on the north side of Albany Avenue between Garden and Bedford Streets.
  • Traffic sign installation will occur project-wide.
  • Expect partial lane closures and minor traffic delays during sidewalk and traffic signal work this week.

Schedule: Week of May 11, 2020*

Normal Work Hours: 7:00am – 5:00pm, Monday-Friday

  • Tree, flower, ornamental grass, and shrub planting continues on Albany Avenue.
  • Sidewalk demolition will occur on the northwest corner of Vine Street at Albany Avenue.
  • Concrete sidewalks and driveway aprons installation continue on the north side of Albany Avenue between Irving and Bedford Streets.
  • Granite curb installation continues on the north side of Albany Avenue at Vine Street and also between Irving and Magnolia Streets.
  • Installation of electrical conduit and decorative lighting will occur on the north side of Albany Avenue between Irving and Magnolia Streets.
  • Expect partial lane closures and minor traffic delays during sidewalk and curb installation this week.

*weather permitting

 Business access will be maintained. All travel lanes on Albany will remain open before 9am and after 3pm; during other hours, partial lane closures may occur. Traffic will be maintained in both directions on Homestead and Westbourne. Hartford Police will assist motorists.

Do you have questions or concerns? Contact Kimberli Owens at (860)-263-8533 or email kimberli.owens@ct.gov.

You may also visit their website at http://www.albanyavenuehartfordproject.com for project updates!

For the latest project photos, visit: http://www.albanyavenuehartfordproject.com/home/photos/.