The Route 44 (Albany Avenue) Safety Improvements Project website is updated with the following:
Schedule: Week of January 25, 2021*
Normal Work Hours: 7:00am–5:00pm, Monday-Friday
Punch list work continues.
New parking signs will be installed this week on Irving and Magnolia Streets.
Project planning and coordination to complete all contract work continues.
Traffic Impacts: No traffic impacts are expected this week.
LOOKING AHEAD: Installation of the remaining project street lights has been scheduled for next month.
Contact Kimberli Owens in the field office at (860) 263-8533. Office Hours: Monday–Friday, 7:00am–3:30pm. Visit albanyavenuehartfordproject.com for updates!
*weather permitting