Route 44 (Albany Avenue) Safety Improvements Project Update

According to the project team, the Route 44 (Albany Avenue) Safety Improvements Project reached substantial completion in fall 2020.  All punch list items, and remaining contract work will be completed as weather allows. Landscaping is set to resume in the spring.

The Project Team will continue to keep the public informed via their email list, the Project website and community meetings. They will also continue to communicate directly with stakeholders—including property owners, merchants, and residents—when they are notified by the Contractor of work that will impact your area.

The Safety On the Avenue website has been updated with the following new schedule content:

Schedule: Week of March 1, 2021*

Hours of Operations: 7:00am–3:30pm, Monday-Friday

  • No construction work is scheduled for this week.
  • Planning and coordination to complete all contract work continues.
  • Punch list work will continue as weather permits. Landscaping is scheduled to resume in the spring.
  • Traffic Impacts: No traffic impacts are expected.

*weather permitting

You may also visit albanyavenuehartfordproject.com for Project updates!