Route 44 Safety Improvement Project Update For The Week Of November 26 & December 3

 

KODAK Digital Still Camera

Week of November 26, 2018
Normal Work Hours: 7:00am – 5:00pm, Monday-Friday

· Asphalt paving will occur in various locations throughout the project area.

· Installation of lighting and electrical wires will continue between Homestead and Edgewood. Traffic signal installation will also occur throughout the project area.

· Installation of brick pavers will continue on the northwest corner of Albany and Woodland (in front of Artists Collective); between Cabot and Edgewood (near Bank of America); and also on the west side of Homestead.

————————————–

Week of December 3, 2018
Normal Work Hours: 7:00am – 5:00pm, Monday-Friday

· Asphalt paving will occur in various locations throughout the project area.

· Installation of lighting and electrical wires will continue between Homestead and Edgewood. Traffic signal installation will also occur throughout the project area.

· Installation of brick pavers will continue on the northwest corner of Albany and Woodland (in front of Artists Collective); between Cabot and Edgewood (near Bank of America); and also on the west side of Homestead.