Baltazar installed the Burton Street Project sign on the corner of Albany Avenue

CNG installing underground high pressure gas lines on Irving Street

Another picture of the high pressure gas line installation

Baltazar completing their underground temporary water main on Burton Street, with testing and paving to follow shortly thereafter.

The temporary water main as it runs down the side of the Burton Street

Baltazar saw cutting to connect to the main sewer trunk at the intersection of Burton St. and Albany Avenue