Schedule: Week of April 22, 2019*
Normal Work Hours: 7:00am – 5:00pm, Monday-Friday
- Drainage and utility work continues on the north side of Albany and Blue Hills.
- Granite curb installation continues on the north side of Albany between Oakland and Deerfield.
- Installation of light pole foundations, conduit, and temporary illumination continues on the north side of Albany between Woodland and Deerfield.
- Preparation work for new sidewalks and driveway aprons continues on the north side of Albany between Woodland and Oakland.
Schedule: Week of April 29, 2019*
Normal Work Hours: 7:00am – 5:00pm, Monday-Friday
- Granite curb installation continues on the north side of Albany between Oakland and Lenox.
- Installation of light pole foundations, conduit, and temporary illumination continues on the north side of Albany between Oakland and Lenox.
- Installation of concrete sidewalks and driveway aprons will begin on the north side of Albany between Woodland and Oakland.
- Brick paver installation continues on the south side of Albany between Cabot and Edgewood.
*weather permitting
Business access will be maintained. All travel lanes on Albany will remain open before 9am and after 3pm; during other hours, partial lane closures may occur. Traffic will be maintained in both directions on Homestead and Westbourne. Hartford Police will assist motorists.
The project field office, located at 1229 Albany Avenue, is open Monday-Friday from 7:00am to 3:30pm. If you have any questions about the project, please stop in and see us. If you have project-related business or pedestrian access concerns, please contact Kimberli Owens at (860)263-8533.